Wednesday, February 2, 2011

Three steps to a better business


 

Achieving operational effectiveness through innovative design

SA Water is the major tenant at SA Water House. The organisation provides water quality testing, research and a public awareness role for the state of South Australia. SA Water House was built via an integrated design programme led by SA Water and workplace strategy consultants DEGW, in conjunction with the building owner, the Catholic Archdiocese and the development team headed by HASSELL. The design process relied heavily on objectives generated from SA Water's cultural change programme, and developed through a strategic briefing process undertaken by DEGW.
The building houses the Australian Water Quality Centre (AWQC) (including both laboratories and workspace), a business unit of SA Water internationally recognised for excellence in providing scientific services for water, wastewater and sludge, and the Learning Centre (LC) - a new capability connecting SA Water with the general public and, in particular, school children. The Centre also houses the Australia Asian Water Centre (AAWC) which includes various water industry bodies who display materials, organise forums and hold meetings. Another government organisation, the Environmental Protection Agency (EPA), is a sub-tenant.
SA Water is a statutory body whose operations are subject to public and political scrutiny. Its function also means SA Water House is a site of Critical National Infrastructure. These constraints, in combination with the desire for an egalitarian workspace, in-house water testing laboratories, a strong client interface and public learning space placed some unique requirements on the commercial building and fit-out.
Significantly, the building outcome is the result of an extensive culture change programme initiated within SA Water (in 2002) after an internal review identified a number of significant challenges to the organisation. These included changing business requirements, a disconnected metropolitan presence across three sites, substandard accommodation, a pressing need to attract (and retain) a new generation of employees in the face of imminent generational change and a skills shortfall. In short, the organisation's operational effectiveness was in jeopardy.
In response to these issues, and targeting world leadership in water quality and sustainability, SA Water developed a long term business and accommodation strategy based on three key change processes: a holistic process of change - the changed management defined the accommodation strategy (not the other way around); extensive consultation across the organisation to review/reinvent ‘how we work', and reinventing the building procurement process.
The intent behind the innovative approach, process and design of this project - based on first principles, was to deeply instill social, environmental and financial sustainability. In addition to addressing property challenges, the development of SA Water House was seen as a powerful mechanism for continuing to drive wider organisational change and transformation. The outcome was a ‘great project team' between SA Water, key consultants (private and government) and the development team. From the start, interaction was based on a high degree of transparency, engagement, trust, knowledge and ‘pain' and ‘gain' sharing.
The intent is encapsulated by Anne Howe, the new Chief Executive of SA Water who stated in 2001, at the beginning of the process, that: "a new workplace that encourages interaction, team work, and greater efficiency and effectiveness is required to better support our people and accelerate continual innovation."
Workplace and Performance Improvements: the change management process, orchestrated by SA Water's People and Culture department, generated staff feedback and longitudinal data which provided the foundation of the design development. DEGW undertook the strategic briefing and initial workplace survey (2005), accommodation strategy (2006) and post occupancy survey (2009). Their post occupancy process included an online workplace survey (WPS), focus groups and statistical survey analysis. An indoor environmental quality (IEQ)-focused post occupancy survey was also conducted by CETEC and a travel survey undertaken by SA Water.
From the initial briefing stages (2005-2008) ten project principles were distilled to guide design and development. The post occupancy survey has shown that all ten principles have been realised as a result of the co-location to SA Water House (see image 5).
Workplace Survey Summary: the survey results show that the organisation has made significant improvements to the physical workplace and the way people work. The high level findings of the post occupancy survey shows that SA Water House: helps create the right culture for SA Water; makes staff more productive by enabling informal collaboration; has significantly increased staff pride and satisfaction; has produced an overall change in workplace performance.
Of the 13 high level workplace categories measured, the Workplace Image and Layout category showed the largest positive change in performance. At the other end of the scale, the negative ‘at your desk' response highlights the perennial productivity issue associated with balancing collaborative and individual work in an open plan environment. Quiet rooms are available and alternative space use is encouraged but the organisation acknowledges improved protocols and processes are needed (see image 6).
The poorer than expected performance of the Indoor Air Quality was mainly attributed to issues with temperature, and is currently being addressed as part of the ongoing tuning of the building systems.
Factors affecting Productivity: DEGW's statistical modelling of the post occupancy outcomes shows that productivity is not a simple measure but a function of a combination of workplace factors. It includes: the ability to concentrate; the capacity for informal meetings and collaborations; having everything needed to work effectively.
Being able to pinpoint and tweak those workplace elements which are underperforming means performance, and therefore workplace effectiveness, can be recalibrated over time.
These enhanced productivity factors in combination with high levels of natural light, energy efficiency, water efficiency, low volatile organic compound (VOC) materials, improved IT capability and improved staff engagement indicates the building sets a new standard in office accommodation within Australia. The change to culture and accommodation has also repositioned SA Water as an employer of choice. This has been demonstrated by the fact that 440 graduate applications were received in 2009, compared to an average of 150 in previous years.http://static.worldarchitecturenews.com/news_images/15584_4_SA4.jpghttp://static.worldarchitecturenews.com/news_images/15584_3_SA3.jpghttp://static.worldarchitecturenews.com/news_images/15584_2_SA2.jpghttp://static.worldarchitecturenews.com/news_images/15584_1_SA1.jpghttp://static.worldarchitecturenews.com/news_images/15584_5_chart%202.jpghttp://static.worldarchitecturenews.com/news_images/15584_6_chart%201.jpg

No comments: